Earned Value Problems Discussion Question
Are you stressed by poor grades and tight deadlines? We have your back. We can do this or a different assignment for you at an affordable price. Use customdissertations.org writing services to score better and meet your deadlines.
Order a Similar Paper Order a Different Paper
Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
1. During a project, Earned Value Analysis is performed and gives the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000
B. CV: +100,000; SV: +120,000
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,000
2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B. The project’s deliverables have all been finished. The project came in ahead of schedule but on budget.
C. The project’s deliverables have all been finished. The project came in on schedule but over budget.
3.You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000.
What is right?
A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000
We offer CUSTOM-WRITTEN, CONFIDENTIAL, ORIGINAL, and PRIVATE writing services. Kindly click on the ORDER NOW button to receive an A++ paper from our masters- and PhD writers.
Get a 10% discount on your order using the following coupon code SAVE10
Order a Similar Paper Order a Different Paper